Project OverviewU-5702 will improve access management add driveways and travel time by widening a 9.7-mile stretch of the road to three northbound and three southbound thru lanes. The project encompasses College Road between New Centre Drive and Carolina Beach Road.Segment A right-of-way is delayed from 2022 to 2023 and construction is delayed from 2025 to 2026 Segment B construction is no longer funded in the 2020-2029 STIP it was originally scheduled to begin 2029.Project Cost 97.4 million
🔍 Key Information
📄
Tender Reference No.
446571824
📅
Publication Date
20 Aug 2019
💰
Estimated Value
97400000
🌐
Sector
Roadways
📅
Deadline
31 Dec 2026
📝
Notice Type
Projects
📍
Location
United states
📑
Contract Duration
7 Years 4 Months 11 Days
📁