Description:
This project was proposed by SDG&E as a reliability transmission solution to address several thermal overloads in the 69 kV transmission system due to the charging/discharging of Valley Center energy storage. The estimated cost for this project is $51 million with a targeted in-service date of 2028.
New 5-mile double circuit 69 kV line (one pole structure) to create two new lines that will connect to Valley Center substation.
One circuit will connect to a de-energized line TL99901 to form a new Valley Center – Escondido 69 kV line.
One circuit will tap into TL688 to create Valley Center – Escondido – Lilac 3-terminal 69 kV line.
De-energize TL681A Ash – Ash Tap.
Reconductor 0.1 miles of TL689E Felicita – Felicita Tap.
Reconductor the underground section of the existing TL99901.
Objectives
Improve system reliability and avoid thermal overloads of 69 kV transmission lines which occur in scenarios were Valley Center energy storage is dispatched either in charging or discharging mode.
🔍 Key Information
📄
Tender Reference No.
504487320
📅
Publication Date
04 Jun 2024
💰
Estimated Value
USD 51000000
🌐
Sector
Energy, Power and Electrical
📅
Deadline
31 Dec 2028
📝
Notice Type
Projects
📍
Location
United states
📑
Contract Duration
4 Years 6 Months 27 Days
📁