Scope of Work:
Vaca-Plainfield 60 kV Line Reconductoring Project.
Description:
Vaca-Plainfield 60 kV line serves load within the city of Winters and Plainfield in the Sacramento area. The Plainfield substation is currently radially served from the Vaca - Plainfield 60 kV line while the source from Nicolaus-Plainfield 60 kV line is normally open. The load serving capability in this area has been limited due to capacity constraint on transmission lines and the radial setup. A P0 contingency overload was observed on the Vaca-Plainfield 60 kV line in the near term. Reconductoring the Vaca-Plainfield 60 kV (about 30 miles) line to achieve minimum conductor rating of 635 amps for summer normal and 741 amps for summer emergency rating
mitigate these constraints.
The ISO recommends approval of the Vaca-Plainfield 60 kV Line Reconductoring Project which includes the following scope:
• Reconductor Vaca-Plainfield 60 kV (about 30 miles) to achieve minimum conductor rating of 635 amps for summer normal and 741 amps for summer emergency rating; and
• Upgrade limiting components as necessary to achieve full conductor capacity.
The total estimated cost of this project is $34M - $68M with an expected in-service date of May 2030 or earlier. Operating solutions will be relied upon in the interim.
🔍 Key Information
📄
Tender Reference No.
504882433
📅
Publication Date
13 Jun 2024
💰
Estimated Value
N/A
🌐
Sector
Energy, Power and Electrical
📅
Deadline
31 May 2030
📝
Notice Type
Projects
📍
Location
United states
📑
Contract Duration
5 Years 11 Months 18 Days
📁