📋 Tender Overview
Scope :
Ubungo – Dar II Line is a 400kV overhead line with a length of 50km from Ubungo, Dar es Salaam, Tanzania, to Dar-2, Dar es Salaam, Tanzania.
The project is expected to be commissioned in 2035.
Description
Ubungo – Dar II Line is an overhead line that will be operated by Tanzania Electric Supply. The line will carry alternating current (AC) through double circuit cable.
Approximately $14.71m was financed by the authorities to undertake the construction works of the project.
Ubungo – Dar II Line project development status
The construction works on the Ubungo – Dar II Line project will be commenced in 2033 and commissioning is expected in 2035.