📋 Tender Overview
Project Description: The sanitary sewer portion of this project consists of evaluating the sewer prior to construction, and in-situ relining and repairs will be performed as required by condition assessment. The storm sewer portion of this project consists of approximately 600 meters of storm sewer pipe, a total of 9 manholes, 1 water quality unit, 1 outfall structure, and 18 catch basins to be replaced. A total of 28 lateral service connections will be installed. The watermain portion of this project consists of replacing the existing watermain with approximately 420 meters of watermain. A total of 28 water services and 4 fire hydrants will be replaced. The concrete curb will be installed, and the paved roadway will be replaced as part of the reconstruction. Design to commence in 2026, with construction in 2027.