📋 Tender Overview
Scope of Work:
Tejon area Reinforcement Project.
Description:
The Tejon area is served by three 70kV lines. The projected local load growth, including an additional 50 MW load at San Bernard substation and 45.5 MW load at Tejon 70kV substation, as indicated in section B3.7.5 of Appendix B, results in thermal overloads observed on the Wheeler Ridge – Tejon, Wheeler Ridge – San Bernard and San Bernard – Tejon 70kV lines in all near-term and long-term Summer Peak scenarios under P3 contingency conditions. This project mitigates the NERC TPL-001-5 Category P3 violations along with increasing the load serving capability and improves customer reliability in the area. This project will add an estimated 104 MW of load-serving capacity to the Tejon area.
The ISO recommends approval of the Tejon Area Reinforcement Project which includes the following:
• Reconductor of the Wheeler Ridge – Tejon 70kV line;
• Reconductor of the Wheeler Ridge – San Bernard 70kV line; and
• Reconductor of the San Bernard – Tejon 70kV line and replace the limiting disconnect switches.
The estimated to cost of the project is $28 - $56 million with an estimated completion date of 2029.