Project : OPS-004-07
Project Description : This program covers the rehabilitation of existing sidewalks citywide. There are 978 kms of sidewalks in the City, of which 6 kms are in "Poor" condition and 74 kms are in "Fair" condition. Based on a 40-year replacement cycle, the perpetual annual cost for the replacement of this infrastructure is approximately $3 million. This would be in addition to the approximately $10.5 million required to address all "Poor" and "Fair" sidewalks and to widen the sidewalks to AODA standards at the time of replacement. From a risk management point of view, annual funding should be increased to reduce trip and fall claims. Effective January 1, 2016, the Accessibility for Ontarians with Disabilities Act (AODA) required width of sidewalks to increase from 1.2 meters to 1.5 meters. This increases the cost of sidewalk replacements. As the change is implemented, Administration is including the increased costs in budget projections