📋 Tender Overview
Description :
I-95 Scudder Falls Bridge Replacement project involves much more than a replacement of the current
functionally obsolete four-lane Scudder Falls Bridge. The project also will include safety upgrades to the
two highway interchanges at both ends of the bridge, widening of I-95 to the inside from the bridge to
Route 322 in Pennsylvania, and construction of shoulders on the bridge crossing to handle breakdowns
and emergencies. The two inside shoulder lanes would have the capacity to serve proposed bus/rapid
transit routes.
This project is planned to: (1) Widen I-95 from PA 332 to the inside by adding one travel lane in each
direction through utilization of the current grass median along that roadway stretch. (2) Reconfigure the
Taylorsville Road Interchange in Lower Makefield Twp., PA by eliminating the existing western
southbound off-ramp and modifications to I-95 acceleration and deceleration lanes. (3) Replace the
existing outdated four-lane Scudder Falls Bridge with an entirely new structure on the upstream side
with overlapping of the current bridge footprint. The new structure would have six lanes of through
traffic (three in each direction) with two auxiliary northbound lanes for entry/exit travel and one auxiliary
southbound lane entry/exit travel. The recommended option calls for full inside and outside roadway
shoulders and bicycle and pedestrian facility on the upstream side of the bridge's southbound span; and
(4) Reconstruct and reconfigure the Route 29 interchange through the use of roundabouts. This option
would avoid traffic signals, resulting in a folded diamond interchange with two roundabout intersections
at the ramps with I-95. Bypasses for NJ Route 29 northbound and southbound traffic would be retained
and improved acceleration and deceleration lanes will be provided onto I-95. ROUTE (MILEPOSTS): I-95 Mercer (0 - 2) COUNTY: Mercer County S5
Cost ($ Millions) $512.000