Description : The first project will focus on Western Acres. Installation of a new liftstation to replace the existing liftstation at Western Acres, which will pump effluent for the full 301 lot buildout to the City of Prince George sanitary system and connect to a manhole located at the intersection of Leland Road and Bunce Road. Effluent from Western Acres will be treated at the City of Prince George Wastewater Treatment Centre at Lansdowne Road. The existing lagoon cells 1, 2 and 3; and the engineered wetland, would be taken offline, and the existing piping abandoned. Discharge restrictions primarily limit existing wastewater treatment capability to Hiller Creek. Treated and seasonally stored effluent cannot be discharged as designed to Hiller Creek since the creek’s low or nonexistent flow does not allow for adequate dilution as required by the permit. Future projects will include Danson and BCR Lagoons. The rationale for this work is because of new federal discharge regulations.