Scope of Work:
Rio Oso-W. Sacramento Reconductoring Project.
Description:
Thermal overloads and voltage criteria violations were observed in the 115 kV and 60 kV transmission system between Vaca Dixon, Davis, Rio Oso, and Brighton substations. The overloads were on the Woodlan-Davis 115 kV line, Brighton-Davis 115 kV line, Rio Oso-West Sacramento 115 kV lines and the Vaca Dixon 115/60 kV transformer bank 5 under category P1- P7 contingency conditions. The Vaca Dixon Reinforcement Project was approved in the 2017- 2018 TPP to address these issues in the area. However, due to aging infrastructure, the re-rate of the Rio Oso-West Sacramento 115 kV line (as a part of Vaca-Dixon Reinforcement project) is no longer viable. In addition, substantial distribution load interconnections have been requested in this area. Altering the scope from rerating the Rio Oso-West Sacramento 115 kV line to reconductoring approximately 26 miles of this Rio Oso-West Sacramento line would effectively mitigate these issues.
The ISO recommends approval of the Rio Oso-West Sacramento Reconductoring Project with the following scope:
• Reconductoring of the Rio Oso – West Sacramento 115 kV line from 040/291 to 013/095A (about 26 miles).
The total estimated cost of this project is $48.7M -$97.4M, with an expected in-service date of 5 years from its start. Operating solutions will be relied upon in the interim.