Scope This project will replace the bridge over Deep Run at OConnor Road. Three foot shoulders are plannedon both sides of the road. The estimated total cost has increased from 6.399 to 6.666 million due to increases in ROW acquisition costs and refined construction cost estimates. Engineering funds were first included in the FY 2014-2017 TIP. FY 2022 engineering funds are tocomplete final design after NEPA approval.
🔍 Key Information
📄
Tender Reference No.
465515105
📅
Publication Date
13 Sep 2021
💰
Estimated Value
USD 6666000
🌐
Sector
Roadways
📅
Deadline
31 Dec 2026
📝
Notice Type
Projects
📍
Location
United states
📑
Contract Duration
5 Years 3 Months 18 Days
📁