Scope of Work:
Expansion of Master Gas System network (MGS) from SHEDGUM to east-west pump stations-1 (EWPS-1).
Descripiton:
Expansion of the MGS from SHEDGUM to EWPS-1 contract is valued at SAR 344.6 million. The contract duration is 40 months for SHEDGUM to EWPS-1.
Package 3: Laying 56-inch east-west gas pipelines three and four from EWPS-1 to Shedgum, covering 56 kilometres (km).
π Key Information
π
Tender Reference No.
501151392
π
Publication Date
29 May 2024
π°
Estimated Value
N/A
π
Sector
Engineering
π
Deadline
30 Sep 2027
π
Notice Type
Projects
π
Location
Saudi arabia
π
Contract Duration
3 Years 4 Months 1 Day