📋 Tender Overview
scope
SMART is receiving supplemental funding from TIRCP to facilitate expeditious completion of Sonoma
County Airport to Windsor construction and completion of project development activities necessary to
begin construction to Healdsburg, maintaining federal grants and additional local funds provided to the
project and fully completing the project components funded in TIRCP Cycle 3. Funding will allow for
design-build contracting methods to be used for completion of Windsor construction, which was 30%
complete when suspended in 2021, and to advance Healdsburg through design and into construction
with leveraged RM 3 funding