📋 Tender Overview
Scope : To Construct Kanpur Metro Line-2’s Package KNPCC-12 in Uttar Pradesh
Ceigall India bored and concreted the first pile for Package KNPCC-12 of Kanpur Metro’s 8.38 km Line-2 which will connect Agriculture University and Barra-8.
4.3 km long Package KNPCC-12 of the 32.38 km Kanpur Metro Phase 1 project consists of 2 disjointed elevated sections on either side of underground Package KNPCC-11 which was awarded for construction to KPIL – Gulermak JV in December 2023.
Uttar Pradesh Metro Rail Corporation (UPMRC) had awarded Ceigall with KNPCC-12’s Rs. 427.11 crore contract in March 2024 with a 30 month deadline.
At 3.745 km, the southern section of KNPCC-12’s viaduct will connect Double Pullia Ramp and Barra-8 with 4 elevated stations at Vijay Nagar Chauraha, Shastri Chowk, Barra-7 Station and Barra-8. On the northern-end of the line, past Rawatpur Interchange Station, a small 557.8m viaduct will be built with 1 elevated station at Agriculture University next to Line-2’s Agriculture University Depot.
Ceigall had started casting pier caps for the line’s viaduct at the yard in June. Per UPMRC’s X post, Ceigall will be boring approximately 750 piles for the viaduct and stations’ substructure.