π Tender Overview
Scope:
The Indore Metro is a rapid transit light metro system which is under construction for the city of Indore, India. The total system consists of 10 corridors covering a distance of 124 kilometres (77 mi). This project will cost approximately Rs.12,000 crore (US$1.7 billion).The cost per km will be 182 crores and total cost is 15,000 crores. There will be three types of run β on road, on bridges, and underground in some locations
On June 2024, Ayesa India was declared as the lowest bidder for the Detailed Design Consultant (DDC) contract for electrical & mechanical (E&M) systems of Indore Metro Metro Phase 1 project.
Indore Metro: IN-04 (5 elevated stations) and IN-O5 (7 underground stations) on Yellow Line
The DDC appointed by MPMRCL will be responsible for producing and proposing alternate designs of electrical and mechanical works.
MPMRCL had invited bids for this consultancy service in September 2023 with a Rs. 15.07 crore estimate and 4.4 year contract duration.
During evaluation, bids submitted by LKT β Lombardi JV and STUP Consultants β RINA Consulting JV were found technically non-compliant to the tenderβs conditions and were disqualified.
MPMRCLβs Brief Scope: Engagement of Detailed Design Consultant (DDC) for (a) Electrical & Mechanical (E&M), Part Plumbing, Environmental Control System (ECS), Tunnel Ventilation System (TVS), SES/CFD Simulation & Building Automation System/SCADA system works for Nine (09) Underground Stations including Twin Tunnel, Cut & Cover, Cross-passages, Ramps and (b) Electrical & Mechanical (E&M), Part Plumbing & Building Automating System works for Twenty Four (24) Elevated Stations including associated Viaducts for Indore Metro Rail Project
Bidding is underway for Indore Metroβs 8.6 km underground package IN-05.
On October 2022, Texmaco Rail and Engineering has secured a contract worth Rs 252.88 crore to supply standard gauge ballastless track for Indore Metro Rail project.
The contract was floated by Madhya Pradesh Metro Rail Corporation (MPMRCL). The scope of work includes designing, supplying, installing, testing, and commissioning the ballastless track of standard gauge for the Indore Metro Yellow Line.
The line is likely to be 33.53 km long making a ring line to connect Palasia Railway Station - Rajwara-Airport - Bhawarsala - MR10 - Palasia with 30 stations.
The contract is to be completed in approximately 3.5 years.
Madhya Pradesh Chief Minister performed groundbreaking ceremony for Indore Metro Rail project at MR-10 Road on 14 September 2019. The project will be developed at a cost of Rs 7,500.80 crore. Under the project, a 31.55 km long corridor is proposed to be built in the city. The Metro rail corridor will pass through Nainod, Bhanwarsala intersection, Radisson intersection and Bengali Chauraha. Most of the Metro section will be elevated while a portion of it will be underground. A total of 29 stations will be constructed on the route. The project is e