Scope :
Haimen Offshore Wind Farm Site 1 is a 700MW offshore wind power project. It is planned in South China Sea, Guangdong, China. The project is currently in permitting stage. It will be developed in single phase. The project construction is likely to commence in 2023 and is expected to enter into commercial operation in 2026.
The project is being developed by Sanxia Shantou Chaoyang New Energy Power Generation and is currently owned by China Three Gorges New Energy.
The project cost is expected to be around $1,978.13m. The project will be spread over an area of 96kmΒ² and will be interconnected by 35kV inter-array cable.
The wind power project consists of 100 turbines, each with 7MW nameplate capacity.