ScopeThe U.S. Army Corps of Engineers has proposed a 778 million reconfiguration of the Brandon Road Lock Dam to install a fish-deterrence system that includes an electric barrier bubble barrier acoustic deterrents and flushing lock. The upgrades are meant to reduce the chances invasive carp could slip through while still allowing barge shipping traffic.total construction cost is pegged at 778 million. If approved by Congress the Army Corps says the project would be completed between 2025 and 2027.
🔍 Key Information
📄
Tender Reference No.
456247940
📅
Publication Date
04 Sep 2020
💰
Estimated Value
778000000
🌐
Sector
Marine
📅
Deadline
31 Dec 2027
📝
Notice Type
Projects
📍
Location
United states
📑
Contract Duration
7 Years 3 Months 27 Days
📁