Project Summary
Approval Date 13 Sep 2023
Planned Completion Date 31 Dec 2028
Last Disbursement Planned Date 31 Dec 2028
Sovereign / Non-Sovereign Sovereign
Sector Power
DAC Sector Code 23630
Commitment U.A 40,000,000
Status Approved
Project General Description
The Project is consistent with the Bankβs Energy Sector Policy 2012 which seeks to promote energy security and increase access to affordable and reliable energy services for household, industrial and commercial use. In addition, the Project is aligned with the Bankβs Climate Change and Green Growth Action Plan (2021-2025) which seeks to promote low carbon development and mitigate as well as boost resilience and adaptation to climate change; the Bankβs Jobs for Youth in Africa Strategy (2016-2025) as it will boost industrial activities, key for youth employment and the Bankβs Gender Strategy (2021-2025) under its pillar 3 which calls for Increasing womenβs access to social services through infrastructure.
Project Objectives
The project development objective is to increase access to clean and reliable electricity supply by reinforcing the transmission system capacity of the Eastern Ethiopia Electricity Grid. The reinforced eastern grid will address voltage drop and power losses in the region and allow more industries and households to be connected to grid electricity, facilitate the full-scale operation of factories connected to the grid and eliminate the use of diesel generators that currently provide base power to the region, and, more importantly, support the launch of the Governmentβs program for irrigated agriculture in the region. Consequently, the project is key to addressing fragility by enhancing the socioeconomic viability of the Eastern Ethiopia region and ultimately, the Federal Republic of Somalia through its eventual interconnection.
Beneficiaries
The proposed project is located in the eastern region of Ethiopia and passes through parts of Somali, Harari and Oromia regional states inhabited by smallholder farming and pastoralist communities. It will have an impact on a population of 2.5 million inhabitants (46% of whom are women) living along the route of the line. The majority of the project is located in the Somali Regional State of Ethiopia, which borders Afar Regional State, Oromia Regional State and the town of Dire Dawa to the west, as well as with Djibouti to the north, the Federal Republic of Somalia to the east and south, and Kenya to the southwest.
Participating Organization
Funding
African Development Fund
Implementing
Ethiopian Electric Power (EEP)