📋 Tender Overview
Project Description: The sanitary sewer portion of this project consists of replacing the existing sanitary sewer with approximately 300 meters of new sewer line. A total of 4 manholes and 30 lateral service connections will be installed. The storm sewer portion of this project consists of replacing the existing storm sewer with approximately 300 meters of new sewer line. A total of 4 manholes and 8 catch basins will be replaced. A total of 30 lateral service connections will also be installed. The watermain portion of this project consists of replacing the existing watermain with approximately 360 meters of new watermain. A total of 30 water services and 2 fire hydrants will be replaced. The concrete sidewalk, concrete curb, and paved roadway will be replaced as part of the reconstruction. Design to commence in 2025, with construction in 2026