Scope of Work:
Diablo Canyon Area 230 kV High Voltage Mitigation Project.
Description:
High voltages above acceptable operating limit of 242 kV have been observed at Diablo Canyon 230 kV substation in real-time operation around or right after midnight when the overall area load was low, the local Los Padres load was low, the local solar farms had zero output, and the transfer on bulk system with SCE was also low.
The ISO is recommending approval of the Diablo Canyon Area 230 kV High Voltage Mitigation Project, which includes the following:
• Install a total of 120 MVAR shunt reactor along with the existing shunt capacitors at Mesa Substation 115 kV bus. The number and size of reactor units will be either 3X40 MVAR or 4X30 MVAR. This will be determined based on power quality requirements (i.e. flicker) as well as in coordination of the LTCs on Mesa 230/115kV transformer banks #2 and #3. The shunt devices will regulate the voltage at Mesa 230 kV bus; and • Remove one or two of the existing 25 MVAR shunt capacitor steps. Alternatives considered were STATCOM installations at Mesa 230 kV, Morro Bay 230 kV, Diablo Canyon 230 kV, or Mesa 115 kV substation, but not recommended due to high costs compared to recommended alternative.
The project has the estimated cost of $35M - $70M and the expected in-service date of May 2027.