📋 Tender Overview
Summary:
Reconstruct Minnetonka Boulevard (CSAH 5) from TH 100 to France Avenue in the City of St. Louis Park.
Purpose & Description:
The existing roadway (last reconstructed in 1952) is nearing the end of its useful life and warrants replacement. Routine maintenance activities (such as overlays and crackseals) are no longer cost effective in preserving assets. The existing sidewalk facilities are located immediately adjacent to the roadway; causing a feeling of discomfort for people walking. The curb has experienced settling, diminishing its ability to collect water and define the roadway edge. The corridor also lacks catch basins, relying on the local storm sewer system to properly manage water in the area. Many intersections include ADA accommodations that do not meet current design requirements, causing challenges for persons with limited mobility. Additionally, county staff has received numerous complaints from residents regarding safety along the corridor due to the 4-lane undivided nature of the roadway.
The proposed project will include new assets, including: pavement, curb, storm water structures, sidewalk, and traffic signals. It is anticipated that a 3-lane typical section will be considered as part of the project development process in an effort to better facilitate vehicle turning movements and provide traffic calming. Specific pedestrian crossing enhancements (such as curb extensions, raised medians, and crossing beacons), bikeway accommodations, and streetscaping features will also be considered as part of the project development process in an effort to benefit people walking and biking. Furthermore, this project presents an opportunity to improve the transition for westbound users as they access Minnetonka Boulevard from West Lake Street.
This project will complement the Green Line Extension LRT Project as it is located within close proximity to the Beltline Boulevard and West Lake Street LRT Stations. Improvements for people walking and biking will improve first/last mile connections for non-motorized users. At this time, it is anticipated that the Green Line extension LRT service will begin operation in 2023.
Scheduling Milestones (major phases only):
Activity Anticipated Timeframe
Planning 2016 - 2019
Design Q1 2021 - Q4 2023
Bid Advertisement Q1 2024
Construction Q2 2024 - Q3 2025
Completion 2026