📋 Tender Overview
Summary:
Reconstruct Lyndale Avenue (County Road 22) from Bridge #27243 over HCRRA to Franklin Avenue (CSAH 5) in the City of
Minneapolis.
Purpose & Description:
The existing roadway (last reconstructed in 1934) is nearing the end of its useful life and warrants replacement. Routine maintenance activities (such as overlays and crackseals) are no longer cost effective in preserving assets. The current roadway environment consists of a 4-lane undivided configuration with no turn lanes provided for people driving. This design has resulted in a high number of crashes, specifically rear-end related. On-street parking is currently permitted on both sides of the roadway throughout all times of day. Sidewalks exist on both sides of the roadway, separated by a boulevard, that provide relatively good accommodations for people walking along Lyndale Avenue (CSAH 22). However, crossing Lyndale Avenue (CSAH 22) can be challenging for people walking, specifically at nonsignalized intersections. These uncomfortable crossing experiences are caused by the current roadway design that does not promote traffic calming among people driving. Also, many of the intersections include pedestrian ramps that do not meet current ADA design standards, with traffic signals lacking Accessible Pedestrian Signals (APS), posing challenges for people with limited mobility. At this time, no dedicated facilities for people biking are provided along this section of Lyndale Avenue (CSAH 22). Additionally, the area in the vicinity of Lyndale Avenue (CSAH 22) at 22nd Street is susceptible to flooding during heavy rain events.
The proposed project will include new assets, including: pavement, curb, storm water structures, sidewalk, and traffic signals. The new roadway environment will be determined as part of the design process after extensive public engagement and environmental analysis.
However, it is anticipated that specific crossing enhancements for people walking (such as curb extensions, raised medians, and crossing beacons) will be considered as this area generates significant pedestrian activity due to the number of commercial businesses surrounding the project area. In addition, the feasibility of dedicated turn lanes at intersections for people driving will be evaluated in an effort to target known crash patterns. This project is Phase 3 (of 3) of capital improvements along the Lyndale Avenue (CSAH 22) corridor in South Minneapolis (initial phases include Capital Projects 2933800 and 2984200 that were completed in the late 2000s/early 2010s).
Scheduling Milestones (major phases only):
Activity Anticipated Timeframe
Planning Q3 2019 - Q4 2021
Design Q1 2022 - Q4 2025
Bid Advertisement Q1 2026
Construction Q1 2026 - Q4 2027
Completion Q2 2028