Scope of Work:
Crazy Horse Canyon (CHCSS)-Salinas-Soledad #1 and #2 115 kV Line Reconductoring Project.
Description:
As a result of the increased demand, thermal overloads were observed on CHCSS-Natividad and Natividad-Salinas line sections of CHCSS-Salinas-Soledad 115 kV line #1 and line #2 during peak loading conditions under P7 contingencies starting near-term and P2 contingency in long term. PG&E proposed a reconductor project to address these overloads.
The ISO is recommending approval of the Crazy Horse Canyon-Salinas-Soledad #1 and #2 115 kV line reconductoring project which includes the following: Reconductor CHCSS-Natividad section of the CHCSS-Salinas-Soledad #1 and #2 115 kV lines to achieve at least 1200 Amps under summer emergency conditions; Reconductor Natividad-Salinas section of the CHCSS-Salinas-Soledad #1 and #2 115 kV lines to achieve at least 1200 Amps under summer emergency conditions; and Upgrade any limiting element(s) on these line sections and associated bus connections to achieve full conductor rating.
Alternatives considered were status quo and looping in the Moss Landing – Del Monte #1 and #2 115 kV double circuit line in Salinas 115 kV but was not recommended due to reliability concerns and space constraint at Salinas substation respectively. In addition, RAS was considered as an alternative, however, the RAS is not feasible due to the number of contingencies and facilities that would need to be monitored. The project has a cost estimate of $54M - $108M and expected in-service date of May 2030.