Scope : Construction work on Chennai Metro Line 5 (Package UG-06/RT-01) in Tamil Nadu
Tata Projects Ltd. (TPL) last week began pouring concrete to cast the first batch of tunnel ring segments for underground Package UG-06/RT-01 of Chennai Metroโs 44.6 km Line-5 which will connect Madhavaram and Sholinganallur via 45 stations.
TPL is responsible for constructing 116.1 km Chennai Metro Phase 2 projectโs 5.8 km underground package UG-06 connecting Kolathur โ Nathamuni. This section with twin tunnels and 5 underground stations is the only underground section of the entire line.
Tataโs casting yard for UG-06 is located in Chennaiโs Perungavur neighborhood, near to Line-3 Package TU-01โs casting yard.
Tata has partnered up with Korea Mould Co. Ltd. to supply segment casting accessories to their casting yard. From back of the hand calculations, I estimate theyโll churn out at least 5200 segments to build this sectionโs twin tunnels.
Chennai Metro Rail Ltd. (CMRL) had awarded Package UG-06โs Rs. 1445.98 crore civil construction contract to TPL in September 2023 with a deadline of 1395 days (3.8 years).
This section will consist of twin TBM-bored tunnels and 5 underground stations at Kolathur Junction, Srinivasa Nagar, Villivakkam Suburban Station (Villivakkam), Villivakkam Bus Terminus and Nathamuni (Villivakkam MTH Road).
Each reinforced concrete tunnel ring will be 1,400mm wide by 275mm thick, and consist of 5 segments + 1 smaller โkeyโ segment.