Railways Engineering Infrastructure and construction Bridges and Tunnels

Bhanupali Bilaspur Beri Tender

πŸ›οΈ RAIL VIKAS NIGAM LIMITED RVNL
πŸ“„ Tender ID: 467889807 πŸ“… Published: 06 Apr 2023

πŸ“‹ Tender Overview

Scope : Construction of Bhanupali-Bilaspur-Beri new railway line in the district Bilaspur of Himachal Pradesh (Package-5).

Dilip Buildcon has been declared as the lowest (L1) bidder for the tender floated by the Rail Vikas Nigam (RVNL) for railway project on percentage rate (EPC project) in the state of Himachal Pradesh.

The project is for construction of tunnels T14, T15 and T16, bridges and formation works from ch 40.430 to 44.925, including slope protection works and allied works in connection with Bhanupali-Bilaspur-Beri new railway line in the district Bilaspur of Himachal Pradesh (Package-5). The bid project cost is Rs 636.98 crore and completion period is 24 months.

On April 2023, H G Infra Engineering has received a letter of acceptance (LoA) dated 4 April, 2023 from Rail Vikas Nigam (RVNL) for a work order in connection with the Bhanupali-Bilaspur-Beri railway line in Himachal Pradesh. RVNL's estimated project cost was Rs 535.15 crore, and the bid quoted by HG Infra was Rs 466.11 crore, making it the lowest bidder (L-1).
The construction work includes foundations, substructure and superstructure along with river training/protection work, earthwork and allied works for viaduct-I and II between ch km 47+415 to km 50+9000, for a total length of 3.485 km.
The contract, which has a completion period of 30 months, is mandated to commence within 42 days from the date of receipt of LoA.

On February 2023, H G Infra Engineering has been declared as L-1 bidder by Rail Vikas Nigam (RVNL) for the Bhanupali-Bilaspur-Beri new railway line project in Bilaspur district of Himachal Pradesh.
The scope of work includes, the construction of foundations, substructure and superstructure along with river training/protection work, earthwork & allied works for viaduct 1 & 2 in between chainage km 47+415 to km 50+900, in connection with Bhanupali-Bilaspur-Beri new railway line. The total length covered is 3.485 km under the project.
RVNL’s estimated cost of the project was Rs 535.15 crore, and HG Infra Engineering was declared the lowest bidder with a bid cost of Rs 466.11 crore. The expected time for executing the work spans 30 months.


πŸ” Key Information

πŸ“„
Tender Reference No.
467889807
πŸ“…
Publication Date
06 Apr 2023
πŸ’°
Estimated Value
84803440
🌐
Sector
Railways
πŸ“…
Deadline
31 Dec 2026
πŸ“
Notice Type
Projects
πŸ“
Location
India
πŸ“‘
Contract Duration
3 Years 8 Months 25 Days

πŸ“ Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
πŸ•’ Submission deadline
59
days remaining Β· 31 Dec 2026
πŸ”” Set Alert

🧭 Quick Facts

Authority RAIL VIKAS NIGAM LIMITED RVNL
Country India
State / UT N/A
Tender Type Project Information
Currency N/A
Similar Tenders
Loading similar tenders…