📋 Tender Overview
Description :This project is to continue the ongoing management activities at Biggera Creek Dam. Whilst a Quantitative Risk Assessment has identified that large scale remedial works may not be justified using risk-based metrics, a 2021 Special Inspection Report has noted that slips like the one that occurred in March 2021 are likely to be an ongoing issue. The Special Inspection Report recommends a comprehensive geotechnical investigation be undertaken. The current timing for a comprehensive geotechnical investigation is 2026 as part of a prescribed 20 year Safety Review. Discussions are underway with the State dam safety Regulator to reschedule the Safety Review to 2022 (after completion of current slip remedial works). It is anticipated that any remedial works identified would require a Planning budget in 2023-24. Delivery of any remedial works will be scheduled in the 10 year program.