📋 Tender Overview
SUMMARY
STATUS
Approved
MEMBER
Azerbaijan
SECTOR
Energy
E&S CATEGORY
Category B
PROJECT NUMBER
000888
FINANCING
APPROVED FUNDING
USD170 million
FINANCING TYPE
Nonsovereign
TIMELINE
CONCEPT REVIEW
August 15, 2024
FINANCING APPROVAL
November 6, 2024
OBJECTIVE
The objective of the project is to support Azerbaijan’s energy transition through expansion of renewable electricity generation.
DESCRIPTION
The Project involves financing the development, construction, operation, and maintenance of two solar photovoltaic (PV) power plants in Azerbaijan – (i) 315 MWac Banka solar PV power plant (Banka Solar); and (ii) 445 MWac Bilasuvar solar PV power plant (Bilasuvar Solar).
ENVIRONMENTAL AND SOCIAL INFORMATION
Applicable Policy and Categorization. The Project is co-financed with EBRD, and its environmental and social (ES) risks and impacts have been assessed in accordance with EBRD’s Environmental and Social Policy (EBRD’s ESP) and related Performance Requirements (PRs). To ensure a harmonized approach in addressing the E&S risks and impacts of the Project, and as permitted under AIIB’s Environmental and Social Policy (AIIB’s ESP), EBRD’s ESP and relevant PRs will apply to the Project in lieu of AIIB’s ESP. AIIB has reviewed the EBRD’s ESP and PRs and is satisfied that: (a) they are consistent with AIIB’s Articles of Agreement and materially consistent with the provisions of AIIB’s ESP, including AIIB’s Environmental and Social Exclusion List (ESEL) and the relevant Environmental and Social Standards (ESSs); and (b) the monitoring procedures that are in place are appropriate for the Projects. EBRD has categorized the ES risks of the Projects as Category B, which is equivalent to Category B if AIIB’s ESP were applicable.
Environmental and Social Instruments. The Sponsor has prepared the environmental and social impact assessment (ESIA) including the management plans, non-technical summary of the ESIA (NTS), stakeholder engagement plan (SEP) and social compliance audit report (SCAR) for each one of two Solar PV projects and Livelihood Restoration Plan (LRP) for Banka Solar and Resettlement Action Plan (RAP) for Bilasuvar Solar. Critical Habitat Assessment (CHA) for both projects have been carried out, and the Biodiversity Management Plans (BMPs) have also been prepared. Lenders’ Environmental and Social Advisor (LESA) hired by the Project carried out environmental and social due diligence (ESDD) and reviewed the project ES documents as well as the Sponsors’ ES management capacity and management systems. The ESDD report and environmental and social action plan (ESAP) have been prepared.
Environmental Aspects. The environmental impacts associated with construction phase of the Project include generation of wastewater, noise and vibration, air quality deterioration due to gaseous emissions and dust, generation of solid waste and hazardous waste including the waste generated from broken/damaged solar panels and accidental spills