π Tender Overview
The Bandeira lithium project, situated in Minas Gerais, Brazil, is currently under development as an underground mine.
It is being developed by Lithium Ionic, a mining company based in Canada.
The projectβs preliminary economic assessment (PEA) was completed in October 2023, and the feasibility study in May 2024.
The Bandeira lithium project is estimated to have a life of mine (LOM) of 14 years with an initial development capital of approximately $266m. The mine is expected to produce 178,000 tonnes per annum (tpa) of spodumene concentrate.
The Bandeira project will feature dual underground mining operations that will optimise the extraction of its deposits.
The primary ore bodies, which account for approximately 83% of the deposit, will be extracted using a bottom-up sublevel stoping method. Concurrently, the secondary ore body in the southβeast, comprising roughly 0.98mt will be mined utilising the room-and-pillar method.
The processing plant is estimated to handle a nominal capacity of 1.3mtpa with an overall Li2O recovery projected to reach 68.9%.
The runβofβmine (ROM) ore will undergo crushing in a primary jaw crusher followed by a secondary cone crusher.
The crushed material will be sorted and screened to remove dilution materials, including schist, and non-lithium-bearing minerals such as feldspar and muscovite. The screen undersize at -0.85mm will be fed through hydrocyclones, which in turn feed a belt filter. The resulting fines product will be stockpiled.
The coarse and mid fractions from the screens will be transferred to the coarse dense media separation (DMS) circuit. The screened ore will be fed through dense medium cyclones and the resultant product will be passed through horizontal dewatering screens to produce a final SC5.5 lithium oxide concentrate. Iron monosilicide (FeSi) will also be recovered through the dewatering screens.
A pivotal infrastructure agreement was secured with Cemig Distribuicao (Cemig) in October 2023, for the construction of a grid power supply infrastructure for the project. The infrastructure includes 3km of new transmission lines from Cemigβs existing power grid to a new substation near the mine. The electrical infrastructure construction is scheduled for completion by the fourth quarter of 2025.