📋 Tender Overview
Scope of Work:
Development of 1.8 GW/ 37GWh Fearna Pumped Hydro Energy Storage (PHES) project.
Description:
The 1.8 GW/ 37GWh Fearna Pumped Hydro Energy Storage (PHES) project has already secured a grid connection offer totaling 1,795 MW. The project envisages the development of tunnels and a new power station connecting SSE Renewables’ existing reservoir at Loch Quoich with an upper reservoir at Loch Fearna. A request for a scoping opinion for the project is currently before Scottish Government ministers and consultation has already commenced with consulting local communities and organisations. Project proponents expect the development to reach commercial operations in the mid-2030s, subject to reaching a final investment decision.