Airports

Vietnam Review Overall Tender

📄 Tender ID: 512942633 📅 Published: 10 Jan 2025

📋 Tender Overview

Appreciating the urgent, determined and fierce working atmosphere at the construction site, the Deputy Prime Minister asked the contractors to report specifically on technological, technical and management solutions to shorten the completion time, while ensuring the highest quality according to the Prime Minister's direction. "If just one package or component project fails to keep up with the overall progress, it will affect the entire project," said the Deputy Prime Minister.

According to the report on the implementation status of the Long Thanh International Airport project by the Ministry of Transport, Component Project 1 (headquarters of state management agencies) will be completed before December 2025, except for the headquarters of animal/plant quarantine agencies (Ministry of Agriculture and Rural Development) which is preparing an investment policy that has not been approved due to lack of capital arrangement. Component 2 project (air traffic management facilities) is on track for completion by December 31, 2025.

Component 3 project (essential works) invested by Vietnam Airports Corporation (ACV) has basically completed 2 packages (construction of fences, leveling); is implementing construction of 7 packages; is selecting contractors for 1 parking lot package; is conducting technical design for 2 projects.

The progress of the main packages, especially package 5.10 (passenger terminal) is meeting the plan to put into operation before August 31, 2026; package 4.6 (runway, taxiway, apron, cargo terminal, hangar, isolation and other works) is expected to be completed before April 30, 2025, 3 months ahead of schedule; package 6.12 (connecting traffic) is expected to be completed before December 31, 2025. Other packages are expected to be completed before August 31, 2026.

Mr. Vu The Phiet, Chairman of the Board of Directors of ACV, emphasized that when the airport is put into operation, the works and items must be synchronous and complete. Therefore, the component projects, service provision packages, as well as connecting traffic routes must be completed and operated smoothly before the passenger terminal project reaches its completion.

The Deputy Prime Minister requested ACV to work with contractors on technology, engineering, additional costs, and economic efficiency when shortening construction time and completing the passenger terminal project.

In addition, ACV is implementing investment steps to build a second runway, expected to be completed in May 2026.

For Component 4 (ground service works), the Civil Aviation Authority of Vietnam (Ministry of Transport) has signed 5/6 urgent bidding packages. Leaders of Vietnam Airlines Corporation (Vietnam Airlines) and Saigon Ground Services Company (SAGS) said that it is expected to complete the items assigned as investors in Component 4 by June 2026. Representatives of Vietjet Aviation Joint Stock Company expressed their desire to be assigned as investors for ground service works, providing airline meals and determined to complete within 12 months.

Emphasizing that Component Project 4 is related to the quality, ranking, standards, utilities, and brand of Long Thanh airport, the Deputy Prime Minister requested the Ministry of Transport and the Civil Aviation Authority of Vietnam to update the progress of 5/6 urgent bidding packages, ensuring quality and compliance with legal procedures; creating conditions for Vietnamese airlines to participate; and studying the plan to assign ACV to implement other bidding packages and items.

Regarding traffic connection, according to the plan, traffic connection to/from Long Thanh airport is by 2 methods: road and rail, including 5 road routes and 3 rail routes.

Road traffic routes include: Bien Hoa-Vung Tau Expressway, Ho Chi Minh City Ring Road 3, Ben Luc-Long Thanh Expressway (these 3 projects are being implemented, expected to be completed in 2025-2026), Ho Chi Minh City-Long Thanh Expressway (currently operating 4 expressway lanes, expected to expand to 8-10 lanes), Ho Chi Minh City Ring Road 4 (investment policy has been submitted).

Regarding railways, including the North-South high-speed railway from Thu Thiem station to Long Thanh (the National Assembly has just approved the investment policy, expected to start construction in 2027 and be completed in 2035); the Thu Thiem-Long Thanh light rail line is expected to be submitted to competent authorities in 2025; urban railways (HCMC is submitting to competent authorities a project to mobilize resources to synchronously invest in urban railways, including this line).

Regarding some current difficulties, Minister of Transport Tran Hong Minh said that if the progress of bid packages is not well coordinated in the overall progress, it could lead to conflicts and additional construction volume, especially in the connection of transport infrastructure, petroleum, and energy; some items and projects are lacking soil and rock.

Vice Chairman of Dong Nai Provincial People's Committee Duong Minh Dung proposed that the Prime Minister direct the early implementation of the second phase of Long Thanh airport's site leveling before putting the first phase into operation; proposed the establishment of a free trade zone within the urban area of ??Long Thanh airport...

🔍 Key Information

📄
Tender Reference No.
512942633
📅
Publication Date
10 Jan 2025
🌐
Sector
Airports
📝
Notice Type
News
📍
Location
Viet nam

📁 Documents & Downloads

No documents found

🏷️ CPV

No CPV found

Need help with this bid?

Our bid experts can help you find, evaluate & win more tenders.

🎧 Talk to Bid Expert
🕒 Submission deadline
0
days remaining · 10 Jan 2025
🔔 Set Alert

🧭 Quick Facts

Authority N/A
Country Viet nam
State / UT N/A
Tender Type Procurement News
Currency Vijay98
Similar Tenders
Loading similar tenders…