📋 Tender Overview
According to the report of the Ministry of Transport, the North-South Expressway Project in the 2021-2025 period is 721.2 km long, passing through 12 provinces and cities, divided into 12 independently operated component projects including 25 construction packages. On January 1, 2023, the first 14 packages were started; the remaining 11 packages will start from January 15 to February 19, 2023. Up to now, the output of project implementation is about 58,721 billion VND, reaching 60.8% of contract value, basically meeting the required progress.
Some projects have good output and construction progress such as: Bai Vot-Ham Nghi, Vung Ang-Bung, Bung-Van Ninh, Chi Thanh-Van Phong, Van Phong-Nha Trang. Some projects have low output, due to the newly handed over land, unfavorable weather conditions (Quang Ngai-Hoai Nhon Expressway Project), or the basic supply of roadbed materials has just been determined (Can Tho-Hau Giang, Hau Giang-Ca Mau Expressway Project).
In addition, the total capital allocated in the annual plan for the North-South Expressway Projects in the 2021-2025 period is VND 93,630 billion (VND 9,521 billion in 2022; VND 47,881 billion in 2023, and VND 36,228 billion in 2024).
In 2024 alone, the North-South Expressway component projects have disbursed 28,967/36,228 billion VND, reaching about 79% of the assigned plan.
Regarding site clearance, the expressway projects have land that is eligible for construction for about 720.94/721.25km, reaching 99.96%; the remaining land (0.19km) is mainly residential land, with complicated relocation procedures.
In particular, the relocation of technical infrastructure works (mainly high-voltage power lines) has been urgently implemented by localities and has had many positive changes. Up to now, 247/256 locations have been completed, and 9/256 locations are being relocated, of which 3 locations of 220-500kV high-voltage power lines in Ha Tinh province are within the scope of handling weak soil roadbeds, affecting the project's progress.
Urgently supplement the supply of materials that are lacking
For the Can Tho-Ca Mau Expressway Project, the remaining demand for sand to complete the embankment work by December 2024 as planned is about 3.9 million m3. Although sufficient supply has been determined, exploitation capacity is still limited due to problems, currently reaching an average of 36,000 m3/day (river sand 26,000 m3/day, sea sand 10,000 m3/day), while the demand is about 86,000 m3/day.
To ensure exploitation capacity, the provinces of Tien Giang, Ben Tre, Vinh Long, An Giang, and Dong Thap need to remove obstacles in supplementing missing resources, completing procedures for granting mines, and approving the resumption of exploitation for mines that stopped exploitation before December 15, 2024 to ensure the source of materials for the construction of the North-South expressway project, Can Tho-Ca Mau section.
In order to complete the target of 3,000km of expressway by 2025, the Ministry of Transport continues to request investors and contractors to coordinate with localities to promptly remove difficulties and obstacles in site clearance, construction material supply, ensure sufficient reserves and capacity to meet the construction progress of projects; develop a reasonable construction organization plan, organize construction in "3 shifts, 4 teams" to speed up construction progress and complete the project.