📋 Tender Overview
The 220kV Vu Thu Transformer Station (TSS) and connection project is invested by EVNNPT, managed by the Northern Power Project Management Board (NPMB), and operated by Power Transmission Company 1.
The 220kV Vu Thu transformer station is located in Tam Quang commune, Vu Thu district, Thai Binh province. The connecting line passes through Tam Quang commune, Dung Nghia commune, Minh Khai commune and Viet Hung commune, Vu Thu district, Thai Binh province.
The project has a total investment of nearly 400 billion VND with the main scale of building a new 220/110/22kV substation with a capacity of 250MVA and building a new 220kV 4-circuit line about 1.9km long.
This project started construction at the end of 2023 and is expected to be completed and energized in April 2025.
Upon completion, the project will receive 220kV electricity from the national grid and from Thai Binh Thermal Power Plant to supply 110kV electricity to the southern region of Thai Binh province, including Vu Thu district, Thai Binh city and neighboring areas, meeting the growing electricity demand of Thai Binh province and the region.
The project helps improve the reliability of power supply in Thai Binh province, prevent overloading of the 110kV grid, and reduce power and power losses on the 110kV grid in the region; improve transmission capacity and reduce losses on the regional grid; and meet the demand for load development in Thai Binh province.
Up to now, the construction part including: Control house, shift rest house, permanent house, fence, fire protection system, equipment support pillar foundation... has been basically completed.
Cable trenching has reached about 60% of the volume, expected to be completed in February 2025; grounding is under construction, reaching 10% of the volume. The 220kV line connection has completed 7/7 pole positions and is organizing to complete wire pulling.
The 220kV - 250MV transformer has been delivered to the construction site on December 25, 2024, and is currently installing the primary equipment/equipment tower. NPMB is targeting to install secondary panels and information cabinets from March 3, 2025; and pull and connect secondary cables from March 5, 2025.
Inspecting the construction site, EVNNPT General Director Pham Le Phu acknowledged and highly appreciated the efforts of NPMB and contractors participating in the project who have made great efforts to complete the large volume of work assigned.
The remaining workload, although not much, requires high technical skills, which are transformer installation and calibration testing. Therefore, the EVNNPT General Director requested the units to concentrate highly, mobilize maximum resources and be determined to complete the project before April 30, 2025 to practically celebrate the 50th anniversary of the liberation of the South and national reunification, practically welcome the success of the 4th EVNNPT Party Congress and welcome the Thai Binh Provincial Party Congress for the 2025-2030 term.