📋 Tender Overview
The 220kV Vung Ang transformer station (TSS) is built in Trai hamlet, Ky Thinh ward, Ky Anh town, Ha Tinh province. The connecting line passes through Ky Loi commune, Ky Thinh ward, Ky Trinh ward, Ky Anh town, Ha Tinh province.
The 35kV power line for self-use passes through the crop land in Ky Thinh ward, Ky Anh town, Ha Tinh province.
The station is designed with 3 voltage levels: 220kV, 110kV and 22kV. The 22kV voltage level is only used to supply power for the station. The station is designed to scale up to 2030 with 2 transformers 220/110/22kV: 2x250MVA (reserve after 2030 the 3rd transformer - 250MVA).
In this phase, a 220/110/22kV -125MVA transformer is installed. The connection line is 2x13.4 km long.
The project is scheduled to be completed in the third quarter of 2024 to ensure electricity supply for Vung Ang Economic Zone and Ha Tinh province. However, due to problems with site clearance compensation, the project is expected to be completed in the first quarter of 2025.
Up to now, the substation construction has reached 90%, expected to be completed in February 2025.. For the connection line, dig and cast foundations at 24/45 locations and erect poles at 5/45 locations.
Currently, the project is facing problems with the foundation position of the 220kV connecting line. The locality has approved the compensation plan for 26/45 foundation positions corresponding to 31/77 households. Payments have been made and the site has been handed over to 33/45 foundation positions. Currently, there are still problems with 12 positions that have not yet been handed over.
The corridor section is currently stuck with 19/45 column spaces, corresponding to 94/154 households that have not yet handed over the site.
At the meeting, EVNNPT Deputy General Director Truong Huu Thanh said: This is a very important project in ensuring electricity for Ha Tinh province and Vung Ang Industrial Park, the project is in the list of projects launched by the Vietnam General Confederation of Labor and EVN.
To ensure the progress of handing over the construction site for energizing the project in the first quarter of 2025, EVNNPT proposed that the People's Committee of Ha Tinh province direct the People's Committee and the Compensation Council of Ky Anh town to continue to mobilize households to measure and check the boundary, and complete before February 17, 2025.
For the remaining 12 foundation locations that have not yet been handed over, EVNNPT recommends that Ha Tinh province, Ky Anh town, and organizations focus on propagating and mobilizing people to receive money according to the draft plan to complete and hand over the site before February 22, 2025.
Regarding the corridor, EVNNPT recommends that the People's Committee of Ky Anh town soon approve specific land prices to implement the next steps. The Compensation Council coordinates with organizations to continue mobilizing 32/68 households that have not cooperated in measuring and drawing boundaries for inventory of perennial crop land, production forest land, houses and structures built on ineligible land at columns 04-07, 07-11 and 14-17, to carry out inventory work, examine land origin, prepare and submit for approval compensation plans; to be completed before February 28, 2025.
In case the compensation plan has been calculated correctly and fully by the town compensation council according to regulations but households still deliberately do not cooperate, obstruct and oppose,..., EVNNPT recommends that the Provincial People's Committee direct the Town People's Committee to urgently develop and complete the procedures for the compulsory land recovery plan.
At the meeting, representatives of EVNNPT and departments, branches and localities of Ha Tinh province clarified a number of difficulties and obstacles in the process of implementing power grid infrastructure investment projects in the area, especially site clearance work; proposed plans to implement projects to ensure progress and quality.
Speaking at the meeting, Vice Chairman of Ha Tinh Provincial People's Committee Tran Bau Ha emphasized: The implementation of the 220kV Vung Ang substation project and connection is very necessary to ensure power supply for Vung Ang Economic Zone in particular and Ha Tinh province in general.
"This is a project that Ha Tinh province has requested the Electricity sector to implement soon, so Ha Tinh province will create all favorable conditions for investors and contractors to ensure progress," the Vice Chairman of Ha Tinh Provincial People's Committee emphasized.
The Vice Chairman of the People's Committee of Ha Tinh province requested relevant departments, branches and localities to focus on removing difficulties and obstacles within their authority so that power grid projects can be implemented according to plan. At the same time, he gave specific opinions on each recommendation and proposal of project investors and assigned relevant departments and branches to advise on solutions within their authority.
The Vice Chairman of the People's Committee of Ha Tinh province assigned the Department of Natural Resources and Environment to coordinate with relevant units to promptly remove obstacles in compensation and site clearance policies.
Request the People's Committee of Ky Anh town to concentrate the entire political system to mobilize households to agree to coordinate in carrying out the inventory records and receive money to hand over the completed site in February 2025.
Along with the mobilization, urgently complete related legal documents to enforce and protect construction if necessary.
The Vice Chairman of the People's Committee of Ha Tinh province requested that after the province hands over the site, the investor should direct the contractor to focus on speeding up the construction progress, ensuring the power supply and handover of the project to meet the set requirements.