(Chinhphu.vn)- Vietnam Electricity Group (EVN) has just officially received and operated the Phu My 2.2 BOT power plant from Mekong Energy Company Limited.
ECONOMY
BUSINESS
EVN officially receives and operates Phu My 2.2 BOT power plant
(Chinhphu.vn)- Vietnam Electricity Group (EVN) has just officially received and operated the Phu My 2.2 BOT power plant from Mekong Energy Company Limited.
0:00
Northern Female
05/02/2025 11:50
EVN officially receives and operates Phu My 2.2 BOT power plant - Photo 1.
Leaders of the Ministry of Industry and Trade, EVN and Mekong Energy Company Limited signed the minutes of handover and acceptance of the Phu My 2.2 BOT power plant - Photo: EVN
The signing ceremony of the minutes of handover and acceptance of the Phu My 2.2 BOT Power Plant between the Ministry of Industry and Trade, Mekong Energy Company Limited and Vietnam Electricity Group (EVN) recently took place in Hanoi.
Phu My 2.2 Power Plant is located in Phu My Power Center, Ba Ria - Vung Tau province, with a total capacity of 715MW using combined cycle gas turbine technology. This is the first BOT (build - operate - transfer) project in Vietnam licensed through international bidding.
The project began commercial operation on February 4, 2005. To date, the plant has completed its operating period as stipulated in the BOT Contract to be transferred to the Vietnamese side, represented by Vietnam Electricity Group (EVN).
This is the second BOT factory to be transferred in this form.
Since its operation, Phu My 2.2 Power Plant has supplied more than 90 billion kWh to the national grid, contributing to ensuring power supply for production and daily life, and socio-economic development of Ba Ria - Vung Tau province in particular and the southern provinces and cities in general.
After taking over, Vietnam Electricity Group will continue to exploit and operate the plant effectively. It is expected that the plant will contribute about 4.6 billion kWh of electricity per year to the national power system, contributing to ensuring national energy security and stabilizing the power system, serving socio-economic development.
Previously, at 0:00 on February 4, 2025, EPS Company (a unit under Power Generation Corporation 3 - JSC) officially took over the operation, maintenance and repair of Phu My 2.2 Power Plant under a service contract with EVN.