Deputy Prime Minister Tran Hong Ha emphasized this requirement at the meeting of the Working Group of Long Thanh International Airport Construction Investment Project (Long Thanh Airport) phase 1, in the form of online Continue to join online, morning of May 28.
Complete site clearance work
Acting Chairman of Dong Nai Provincial People's Committee Vo Tan Duc said that for the T1 construction route, 100% of the site has been basically handed over, while 4,500 m2 of a household will be handed over to the construction contractor on June 3. . For the T2 construction route, there are still 30 households that have not yet relocated or handed over the land and the locality will carry out enforcement after June 30.
Regarding the relocation of electrical technical infrastructure, Long Thanh district coordinated with the contractor to cut off power at 5/10 points that need to be relocated to serve construction, while the medium-low voltage system has completed the paperwork and procedures, and is under construction. Conduct appraisal for implementation.
Dong Nai has completed 21/21 technical infrastructure packages for resettlement areas; 7/11 social infrastructure projects.
"Dong Nai must commit not to slow down the construction progress of the project. Comrades can call to discuss and propose directly if there are any problems, without having to send documents up or down", Deputy Prime Minister the general said.
Regarding the progress of component 2 project (air traffic station, radar stations, radio transceiver stations...), the representative of Vietnam Air Traffic Management Corporation said that the progress of construction and installation of rough parts of the The bidding package is meeting and exceeding requirements. Vietnam Flight Management Corporation has conducted bidding to select consultants to build installation equipment packages, 50% completed and in June will issue bidding documents.
The passenger terminal and runway bidding package may be ahead of schedule
Report to the Deputy Prime Minister on the implementation of component 3 project (passenger terminal, airport construction, cargo terminal 1,...), Mr. Vu The Phiet, General Director of Vietnam Airports Corporation Nam (ACV) said the passenger terminal package was 10-20 days ahead of schedule. The main contractor has submitted a list of equipment in accordance with the bid documents, 90% of the steel structure volume has arrived at the project, expected to be installed from August 2024.
The runway, taxiway, and aircraft apron bidding package aims to complete, calibrate equipment, and calibrate flights on April 30, 2025, 3 months ahead of schedule.
The bidding package for constructing traffic routes connecting the passenger terminal with National Highway 51 and Ho Chi Minh City-Long Thanh-Dau Giay Expressway is being implemented according to the set schedule.
ACV has directed the Project Management Board to review the progress and construction time of the remaining bidding packages to match the progress and avoid conflicts and intersections during the construction of the passenger terminal.
"Equally important is that the completion progress of component projects, especially essential bidding packages, must match, otherwise it will affect the connectivity and progress of the entire project," Mr. Vu The Phiet further exchange.
In addition, ACV leaders also proposed a plan to implement preparations for construction of phase 2 so as not to affect the exploitation activities of phase 1, on the basis of adjusting the project investment policy. phase 1 project.
Bidding packages under component 4 projects cannot yet be bid
Report on the bidding status of bidding packages under project component 4 (including cargo terminal items, aviation logistics area, aircraft maintenance area, meal supply, airline operations center), A representative of the Vietnam Aviation Administration (Ministry of Transport) said the biggest problem is calculating the investor's contribution rate to the State budget throughout the project's life cycle.
Deputy Minister of Planning and Investment Do Thanh Trung said that sharing revenue, profits and risks in projects is an international practice, and must be based on specific operational factors of each industry. The Aviation Department needs to consult and advise on ACV's existing experience in bidding for non-aviation services.
Agreeing with this opinion, Mr. Vu The Phiet proposed that essential items of the project component 4 such as cargo terminal, aviation logistics area, aircraft maintenance area, catering area... must be fully implemented. Urgency, otherwise, even if other component projects are completed ahead of schedule, the whole project will not be able to operate.
The Deputy Prime Minister requested the Ministry of Transport and the Civil Aviation Authority of Vietnam to work with the Bidding Department (Ministry of Planning and Investment) to clearly define and take responsibility for standards and information on services and products to select investors. The company has enough capacity, technology, reputation, and Vietnamese brand, providing the best services, attracting customers in the region, contributing to spreading the nation's identity and traditions, appropriate to its scale. the region's international airport.
"The items of project component 4 will determine the prestige, quality, and competitiveness of an international airport in the region," said the Deputy Prime Minister.
It is known that in Official Dispatch No. 1900/VPCP-CN, issued on March 23, 2024, Deputy Prime Minister Tran Hong Ha assigned the Ministry of Transport to proactively coordinate closely with the ministries: Planning and Investment, Justice, Natural Resources and Environment, and Public Works.