📋 Tender Overview
Deputy Prime Minister Tran Hong Ha emphasized this requirement at the meeting of the Working Group of Long Thanh International Airport Construction Investment Project (Long Thanh Airport) phase 1, in the form of online Continue to join online, morning of May 28.
Complete site clearance work
Acting Chairman of Dong Nai Provincial People's Committee Vo Tan Duc said that for the T1 construction route, 100% of the site has been basically handed over, while 4,500 m2 of a household will be handed over to the construction contractor on June 3. . For the T2 construction route, there are still 30 households that have not yet relocated or handed over the land and the locality will carry out enforcement after June 30.
Regarding the relocation of electrical technical infrastructure, Long Thanh district coordinated with the contractor to cut off power at 5/10 points that need to be relocated to serve construction, while the medium-low voltage system has completed the paperwork and procedures, and is under construction. Conduct appraisal for implementation.
Dong Nai has completed 21/21 technical infrastructure packages for resettlement areas; 7/11 social infrastructure projects.
"Dong Nai must commit not to slow down the construction progress of the project. Comrades can call to discuss and propose directly if there are any problems, without having to send documents up or down", Deputy Prime Minister the general said.
Regarding the progress of component 2 project (air traffic station, radar stations, radio transceiver stations...), the representative of Vietnam Air Traffic Management Corporation said that the progress of construction and installation of rough parts of the The bidding package is meeting and exceeding requirements. Vietnam Flight Management Corporation has conducted bidding to select consultants to build installation equipment packages, 50% completed and in June will issue bidding documents.