📋 Tender Overview
This is a level I energy project, invested by EVNNPT, managed by CPMB, and operated by Power Transmission Company 1. The project was approved by the People's Committee of Nghe An province in terms of investment policy and the investor in Decision No. 123/QD-UBND (dated November 11, 2024).
The 220 kV Do Luong – Nam Cam Transmission Line Project is built in Do Luong, Nghi Loc and Hung Nguyen districts of Nghe An province. The project has a scale of building 2 circuits of 220kV lines from the 220kV Do Luong transformer station to the 220kV Nam Cam transformer station with a length of about 37 km. Particularly, the section from G4 - G6 (length of about 4 km) is built with 4 circuits to combine with 2 circuits of the 110kV Do Luong - Nam Dan line.
The expansion of the bay at the 220kV Do Luong substation will install equipment for 2 bays of 220kV in the 220kV Do Luong substation (existing) and connect the information system for the 220kV Do Luong - Nam Cam line. The total investment capital of the project is nearly 557 billion VND.
Once completed, the project will meet the electricity demand for the load in the Central region, where some important existing and future industrial loads of Nghe An province are concentrated, contributing to promoting the socio-economic development of Nghe An province.
At the same time, strengthening the power grid connection between Northern Vietnam and Laos contributes to solving the power source tension in the Northern region; supporting power lines in the region to enhance the safe and stable operation of the national power system; reducing power loss in the transmission grid, increasing the production and business efficiency of EVN and EVNNPT.
Mr. Le Xuan Hoa, Director of the Central Power Project Management Board, said: This is an important project to ensure electricity supply for Nghe An province - a vibrant economic development area of ??the province with a rapid electricity growth rate, along with serving to release power capacity from Laos to Vietnam according to the commitment of the two governments.
Therefore, CPMB requires units during the construction process to strictly comply with technical regulations and procedures; well manage occupational safety and hygiene, environment; and ensure the quality of construction works.
The CPMB Director requested construction units and supervision consultants to promote the "spirit of 500kV line circuit 3" to strengthen and mobilize forces, closely coordinate with the project management and operation unit and related units to ensure quality and progress of construction, striving to complete energization in 2025 according to the direction of EVNNPT.
The representative of the construction unit committed to mobilizing maximum resources to speed up the project's progress, and at the same time hoped that during the implementation process, the project would receive close coordination from local authorities and people whose projects pass through in site clearance so that the contractor could speed up the progress, meeting the electricity demand of Nghe An province and its localities.
It is known that, up to now, Nghe An province has handed over 68/104 foundation locations (reaching 65.3%), of which Do Luong district handed over 39/49 locations, Hung Nguyen 5/5 locations and Nghi Loc 24/50 locations. The corridor part of the route is undergoing procedures.