Attending the meeting were representatives of relevant departments, branches and localities of Lai Chau province. On the EVNNPT side, there were leaders of the Northern Power Project Management Board (NPMB) and leaders of EVNNPT's professional departments.
Three groups of problems affecting project progress
In Lai Chau province, EVNNPT is implementing 3 projects including Phong Tho 220kV transformer station, Pac Ma 220kV transformer station, Pac Ma - Muong Te 220kV transmission line. Along with that, 2 projects Phong Tho - Than Uyen 220kV transmission line, Than Uyen - Lao Cai 220kV transmission line are in the investment preparation stage. In addition to the very important role in ensuring energy security, releasing the capacity of power plants in Lai Chau province, with a total investment of over 3,651 billion VND, the projects will contribute significantly to the economic growth of this locality.
The 220kV Pac Ma – Muong Te line has a project scale of 2x31 km. The project passes through Muong Te district, Lai Chau province. According to the project plan, it will be energized in the fourth quarter of 2025.
The 220kV Phong Tho - Than Uyen line has a project scale of 2x88 km. The line passes through Phong Tho, Tam Duong, Tan Uyen, Than Uyen districts and Lai Chau city. According to the project plan, it will be energized in the fourth quarter of 2025.
The 220kV Than Uyen – 500kV Lao Cai substation transmission line has a project scale of 2x73.5 km. The project passes through Than Uyen district, Lai Chau province and Van Ban and Bao Thang districts, Lao Cai province. According to the project plan, it will be energized in 2027.
Phong Tho 220kV transformer station has a scale of 2 transformers with a total capacity of 500MVA and 8 110kV feeder bays connected to hydropower plants. According to the plan, the project is expected to be energized in the second quarter of 2025.
Pac Ma 220kV transformer station has a scale of 2 transformers with a total capacity of 500MVA and 6 110kV feeder bays connected to hydropower plants. According to the plan, the project is expected to be energized in the second quarter of 2025.
The Phong Tho 220kV substation, Pac Ma 220kV substation, and Pac Ma - Muong Te 220kV transmission line projects are under construction. However, there are still many problems that need to be resolved soon.
The 220kV Than Uyen - Lao Cai and Phong Tho - Than Uyen transmission line projects are in the investment approval appraisal stage and require the province's decisive participation.
Currently, the projects are facing long-term problems, specifically the main problems related to the unapproved conversion of forest use purposes; unapproved investment policies; and unallocated or leased land.
These problems have made the progress of the projects much slower than planned.
At the meeting, EVNNPT Deputy General Director Hoang Van Tuyen said: In recent times, EVNNPT has ensured safe, continuous and stable operation of the transmission grid in Lai Chau province. Along with that, the Corporation has invested in power lines and transformer stations to serve the socio-economic development of the province.
Currently, many hydroelectric plants are being developed in Lai Chau province. These projects are being implemented to release the capacity of hydroelectric sources in Lai Chau province and neighboring areas to the national grid.
At the same time, strengthen the connection of regional power systems, improve safety, reliability and stability in the operation of regional and national power systems, contribute to ensuring national energy security and increase budget revenue for the province.
To ensure sufficient electricity for economic development and people's lives, on January 3, 2025, the Prime Minister issued Directive No. 01/CT-TTg on proactive solutions to ensure sufficient electricity supply for production, business and people's lives during peak periods in 2025 and the period 2026 - 2030.
Implementing the Prime Minister's directive, EVNNPT is accelerating investment in power transmission grid projects in the Northern region, especially power transmission projects in the Northwest region, to relieve the capacity of hydropower plants in the region.