Attending the workshop were representatives of the Departments of Industry and Trade of 9 provinces in the Central Highlands, the National Electricity System and Market Operation Company Limited (NSMO), the National Power Transmission Corporation (EVNNPT), 98 power plants in the area and partners.
Enhance operational coordination
In his opening speech, Mr. Nguyen Cong Thang, Director of Power Transmission Company 3 (PTC3), said that during the operation of the power system, when overload or full load occurs, the responsibility does not only belong to the PTC3 operating team but also the shared responsibility of all relevant parties.
After more than 4 years of coordination, the power grid in the Central Highlands region has operated safely and reliably, ensuring sufficient electricity supply for the region, contributing to the economic development of localities as well as the region.
The workshop is an opportunity for PTC3, management agencies and renewable energy (RE) power plants in the area to review the difficulties, share lessons learned and find optimal solutions to ensure the power transmission system always operates safely, stably and effectively. At the same time, commit to contributing to strong socio-economic development and reaching out in the new era - the era of the Vietnamese people's rise, the era of international integration and green, sustainable energy conversion.
For that purpose, the Director of PTC3 hopes that partners and enterprises will continue to strengthen coordination between control and operation units and power plants, especially renewable energy, to ensure the system operates synchronously, minimize incidents and optimize generation capacity; strongly apply digital technology, artificial intelligence and automation in monitoring, operating and coordinating the power grid to improve efficiency and forecasting ability; promote cooperation with state management agencies, local authorities and enterprises to remove difficulties in mechanisms and policies, especially the issue of transmitting electricity from renewable energy sources to the national power system.
PTC 3's report said that as of February 2025, this unit is managing 2,338 km of 500kV lines, 3,670 km of 220kV lines, 6 500kV transformer stations, 21 220kV stations with a total transformer capacity of 17,248 MVA. There are currently 98 power plants connected to the grid managed and operated by PTC3, including Khanh Hoa: 3, Phu Yen: 6, Binh Dinh: 6, Gia Lai: 16, Dak Lak: 17, Ninh Thuan: 23, Dak Nong: 8, Lam Dong: 6; Binh Thuan: 13.
Of which, there are 30 factories connected to the transmission grid; 33 factories connected to the busbar of the transmission substation; 30 factories connected to the busbar of other renewable energy factories; the number of factories connected to the 110kV grid of the Central Power Corporation and the Southern Power Corporation but one end is the substation of PTC3 is 6 factories.
Among the 98 connected plants, there are many types of power such as wind power, solar power, hydropower, biomass and thermal power. Of these, only 14 plants belong to EVN, the remaining 84 plants belong to investors other than EVN. In particular, many plants have diverse connection forms such as transitional connection to the transmission grid, to the transformer station busbar or 110kV grid of other power companies. This creates great challenges in ensuring stable grid operation, and at the same time requires close coordination between management units and external investors to maintain safe and efficient power transmission.
In 2024, PTC3 conducted 887 power outages to perform grid maintenance, with 10 grid incidents. However, with the preparation of plans in advance, flexible operation, enhanced solutions, maintenance inspection, and close coordination with power plants in the region, the number of grid incidents in the past year was well controlled, meeting the operational targets and ensuring the incident rate was within the limits assigned by EVNNPT.