Ministry of Industry and Trade held a workshop on "Adjusting the National Power Development Plan for the 2021-2030 period, with a vision to 2050 (Adjusting Power Plan VIII) and strategic environmental assessment report" to complete the project to submit to the Government.
The Ministry of Industry and Trade has coordinated with relevant ministries, branches, agencies and the Institute of Energy to develop the Project to Adjust the Power Plan VIII. Deputy Minister Nguyen Hoang Long emphasized that the comments contributed at the workshop will be an important basis for the Ministry of Industry and Trade to absorb, edit and complete the project, ensuring a sustainable power plan, suitable for practice and meeting the requirements of socio-economic development.
"With the desire to build a feasible Power Plan Adjustment Project VIII in practice, the comments of the experts present today are extremely valuable. The Ministry of Industry and Trade will accept and record the valid comments for editing and completion in the coming time," the Deputy Minister emphasized.
At the workshop, Mr. Tran Ky Phuc, Director of the Institute of Energy (Ministry of Industry and Trade), raised 5 key issues that need to be discussed. First of all, the lessons learned from the implementation of previous power plans.
Second, forecasting electricity consumption demand in the context of socio-economic development.
Third, the orientation for power source development in the 2030-2035 period and vision to 2050, including views on traditional power sources such as coal-fired thermal power, domestic gas-fired thermal power, imported liquefied gas, nuclear power, as well as policies for developing renewable energy and electricity storage systems.
Fourth, the content related to the planning of the development of the transmission grid, especially the inter-regional connection line system.
Finally, there are economic, environmental and governance factors in power planning, including investment promotion policy mechanisms, electricity prices, electricity markets, capital mobilization and specific policies. In particular, there is a need for strong sanctions to handle projects that are behind schedule, in order to ensure effective implementation of the national power plan.
4 electricity demand scenarios
Forecasting electricity demand related to the National Power Development Plan for the 2021-2030 period, with a vision to 2050, Dr. Nguyen Ngoc Hung - Institute of Energy (Ministry of Industry and Trade) proposed 4 specific electricity demand scenarios: Low scenario; Baseline scenario; High scenario; Special high scenario.
Notably, the forecast results of the High Scenario especially show the growth rate of commercial electricity: From 2026-2030: 12.8%/year; 2031-2040: 8.6%/year; 2041-2050: 2.8%/year. Accordingly, the difference with the forecast of the Base Scenario of Power Planning VIII: In 2030: commercial electricity over 56 billion kWh, Pmax over 10.0 GW; in 2050: commercial electricity over 430 billion kWh, Pmax over 71.5 GW. Electricity intensity in 2030: 51.0 kWh/million VND; in 2050: 19.1 kWh/million VND (a decrease of 4.8%/year)
"This scenario reflects electricity demand in the event that the economy accelerates in the 2026-2030 period and continues to maintain high "double-digit" growth for a long time. The scenario also ensures reserves for long-term electricity development," Dr. Nguyen Ngoc Hung analyzed.
Need to update details of renewable energy potential of each locality
Commenting on the adjustment of the Power Plan VIII, Mr. Nguyen Van Duong, researcher of the Power System Development Department (Institute of Energy), said that one of the key issues is to update the details of renewable energy potential in each locality to effectively exploit national resources. At the same time, the research team emphasized the need for backup plans for wind and solar power to cope with the instability of these energy sources.
Actual power system operations in 2023 show that, although the installed capacity is about 1.5 times higher than demand, the North still experiences local power shortages. In the future, when the proportion of wind and solar power increases to 60-70% of total capacity, additional backup will become urgent to ensure energy security.
The research team's assessment also shows that Vietnam's power source structure has undergone significant changes. Before 2010, the power system relied on coal-fired thermal power, hydropower and gas turbines. In the 2011-2019 period, coal-fired power continued to expand. Currently, with the orientation of not developing new coal-fired thermal power and hydropower having almost fully exploited its potential, the power source structure is gradually shifting to renewable energy, with gas turbines playing an intermediary role thanks to their low emissions and flexible operation.
Statistics show that by 2024, the total capacity of the power system will reach about 80 GW, with electricity output exceeding 300 billion kWh. However, some important power sources such as offshore wind power and pumped storage hydropower have only reached 19-62% of the plan, reducing short-term reserve capacity and posing many challenges.
To ensure energy security, Vietnam's power development scenarios focus on two main options: utilizing unused land and converting part of production forest land to develop solar power. Accordingly, the total solar power potential in the baseline scenario is about 295,000 MW, while the high scenario is estimated at 576,000 MW.
It is forecasted that by 2050, Vietnam will achieve its goal of net zero emissions, with renewable energy accounting for the majority. To realize this goal, the transmission system needs to be expanded, while energy storage technology and flexible power sources need to be applied to maintain a stable power system.