On April 20, the delegation of the State Appraisal Council led by Mr. Bui Xuan Dung - Deputy Minister of Construction, Standing Vice Chairman of the Council inspected the route to accept the Cam Lam - Vinh Expressway Project. Good before putting it into operation.
Also attending were Deputy Minister of Transport Le Anh Tuan, representatives of Ninh Thuan, Binh Thuan, Khanh Hoa provinces, consortium of investors, project enterprises...
At the meeting, design consultants, supervision consultants, independent inspection consultants, the council's standing agency... all agreed with the investor's report, requesting the Council to accept it. approved and put the project into operation.
On the local side, representatives of the Department of Transport and the Department of Construction of the three provinces of Khanh Hoa, Binh Thuan and Ninh Thuan also confirmed that the project is eligible for exploitation and use.
Localities also asked investors and relevant agencies to consider investing in phone coverage throughout the area to ensure communication in case of emergency. In addition, Ninh Thuan province also proposed to soon clear the tunnel on the right to facilitate vehicle circulation on the highway.
At the same time, coordinate with the Traffic Police Department - Ministry of Public Security (C08) to conduct fines through the surveillance camera system on the route, research and invest in building rest stops on the route...
The expert group and Council members assessed that the investor's completed project acceptance work was basically in accordance with regulations, met design requirements and had completed related legal procedures. .
The Cam Lam - Vinh Hao Expressway project is basically eligible for the Council to approve the conditional acceptance results according to regulations to put the project into operation and use.
Deputy Minister of Transport Le Anh Tuan - Vice Chairman of the Council highly appreciated the spirit of participation of relevant entities to comply with the Prime Minister's instructions with the motto "overcome the sun, overcome the rain", " Eat quickly, sleep quickly", "only talk forward, don't talk back"...
Along with the capacity and experience of the investor consortium led by Deo Ca Group to complete the project despite many difficulties and challenges.
"For the Vung Mountain tunnel project, the Ministry will have a written report and ask for opinions from the State Inspection Council to deploy investment and put into use both tunnels on the highway," Deputy Minister Le Anh Tuan said. know.
Concluding the meeting, Mr. Bui Xuan Dung, Deputy Minister of Construction, Permanent Vice Chairman of the State Appraisal Council highly appreciated Project Management Board 85, investors, contractors, consultants and related parties for coordinating Coordinate well, closely follow the implementation process, and contribute to project completion.
The Council approved the acceptance results to put the project into operation and use, and at the same time requested the investor to receive opinions from the expert group and relevant parties to review and soon complete the remaining minor shortcomings. .
The Council will issue a written proposal for additional capital to invest in completing and putting into operation both Nui Vung tunnel pipes to ensure exploitation efficiency and minimize risks when exploiting one tunnel. "Because of this BOT project, it is recommended that the parties complete the acceptance documents as soon as possible to create conditions for project enterprises to exploit and ensure financial plans," Deputy Minister Bui Xuan Dung said.
Cam Lam - Vinh Hao Expressway is one of three North - South Expressway component projects invested in the form of public - private partnership. The project has a total investment of 8,925 billion VND, with a length of 78.5km, passing through 3 provinces of Khanh Hoa, Ninh Thuan and Binh Thuan. The joint venture investors are Deo Ca Group, Deo Ca Construction Company and 194 Construction Investment Company.