📋 Tender Overview
The Ministry of the Environment, Climate and Energy has announced a change to the public tender for co-financing investments in the construction of new devices for the production of electricity from solar or wind energy for the period from 2025 to 2029 (code JR EKP SE VE OVE 2025).The change was published in Official Gazette no. 104/2025 and enables unification of the threshold values of devices for investments in solar and wind power plants with a nominal power above one megawatt (MW), regardless of the status of the investor.
The subject of the amended public tender JR EKP SE VE OVE 2025 is the allocation of grants for the co-financing of investments in the construction of new devices for the production of electricity from solar or wind energy (combined with or without battery energy storage devices), the total nominal power of which is:
for solar power plants (SE): above one MW of the nominal power of the device (installed photovoltaic modules) for companies and for communities in the field of energy from renewable sources, established under the conditions set out in the Act on the Promotion of the Use of Renewable Energy Sources (ZSROVE) (RES communities),
for wind power plants (VE): over one MW of nominal power of the device (generator) for companies and for communities RES.
Both the rated power of the device and the connected power of transmission to the power grid, which can be seen from the Consent for the connection of the production device (Consent for connection), must be greater than one MW. In the case of the installation of a battery storage of electricity, its capacity must be at least 0.75 kilowatt hours (kWh) per one kilowatt (kW) of the nominal power of the production device to which it is installed. Investors under this public tender are commercial companies and individual entrepreneurs under the Companies Act (ZGD-1) and cooperatives under the Cooperatives Act (ZZad).
The eligible costs of the operation include:
purchase and installation of production equipment, including supporting substructure,
purchase and installation of a battery storage of electricity,
the associated electrical installation and equipment, including the transformer station, if it is required by the consenting party to connect the device,
preparation and execution of construction, craft and installation works necessary for the operation,
professional supervision worth three percent of the eligible costs of the operation.
The recognized eligible costs of the operation are co-financed with the funds of the European cohesion policy up to a maximum of:
45 percent of recognized eligible costs for production facilities without electricity storage capacity, but not more than:
- 180 euros per one kW of nominal power of the device (for solar power plant and free-standing solar power plant);
- 250 euros per one kW of nominal power of the device (for a solar power plant that will cover outdoor uncovered parking spaces);
- 560 euros per one kW of rated power of the device (for a wind power plant);
30 percent of recognized eligible costs for battery electricity storage, but no more than 225 euros per kWh of electricity storage capacity.
The maximum amount of co-financing that can be allocated to an individual application amounts to a maximum of 25 million euros.
The public tender is financed by means of European cohesion policy from the European Fund for Regional Development. There are two more application deadlines, 6 February 2026 and 5 June 2026.
Link to public tender.