The deputy head of the HODA Ruslan Tikhonchenko got acquainted with the progress of works on the object.The physical-fitness complex is being built on the territory of the Dergachiv Lyceum. All residents of Dergachiv district will be able to use it. Construction work is ongoing here from 2018. They are financed by the State Regional Development Fund oblast and rayon budgets.The institution has already completed the preparatory work laid the foundation mounted the external enclosure structures of the building and the dome. Internal walls and partitions a floor slab of the second floor were equipped and also door and window blocks were installed. At present the installation of external and internal engineering networks as well as the decoration of the premises is almost complete - said the deputy chairman of HODA.After the completion of the work the services of the fitness center will be able to use about 400 people a day. The opening of the fitness center is scheduled for September 2020.