The other day another responsible stage of construction started on one of the man-made structures that form the Zaporizhzhya Megamist the beam bridge over the Staryi Dnipro River. The bridge builders started the third stage of longitudinal approach of the metal structure which will become the basis of the bridge.The third stage involves the approach of the girder structure by 96 meters. As of June 1 the bridge builders pushed the metal structure 68 m towards the island of Khortytsia on the support 2.The total weight of the metal structure is 2410.3 tons. When the third stage of advancing is completed the bridge builders will cover a 128-meter run which is the longest during the construction of bridges throughout Ukraine.It will be recalled that the beam bridge across the Stary Dnipro River is part of the Motorway across the Dnieper River in Zaporizhia which consists of 26 man-made structures 6 transport interchanges and will be 9.1 km long.This long-term construction in 2020 became the flagship of the Presidential program Big Construction .