📋 Tender Overview
- Quality work at risk in drinking water and sanitation work valued at more than S/ 4 millionPasco.- The Comptroller General of the Republic warned that the supervisor and the resident of the work to improve and expand the drinking water and sanitation service in the town of Pampania, district of Santa Ana de Tusi, province Daniel Alcides Carrion, work simultaneously on other public projects despite the fact that their contract requires exclusive dedication.
According to the Control Milestone Report Ndeg002-2026-OCI/0447-SCC (evaluation period from January 28 to February 3, 2026), it was verified that the supervisor performs the same position in three other works carried out by different public entities and in different geographical locations, while the resident does the same in five other works at the same time.
This duplication of functions generates the risk that the work, whose investment exceeds S/ 4 million, does not have the technical direction and permanent surveillance necessary to guarantee that the work is carried out correctly and under the quality standards of the technical file.
In addition, it was identified that the project was executed without the approval of the Archaeological Monitoring Plan by the Deconcentrated Body of Culture of Pasco, a mandatory document to prevent possible damage to cultural heritage during the execution of the excavation work.
The work has been paralyzed since January 16, 2026 due to climatic factors; However, the corresponding suspension document has not been signed between the municipality and those responsible for the project.
The control report was notified to the mayor of the District Municipality of Santa Ana de Tusi to urgently adopt the necessary measures and guarantee that the executing company and supervision comply with the personnel offered.
Pasco, March 5, 2026
Communications Management
PRESS RELEASE Ndeg229-2026-CG/GCOM