- Comptrollers Office identifies that contractor installed unsealed sinks, there are leaks in ceilings and non-existent work for more than S/ 80 thousandJunin.- The Comptroller General of the Republic warned the Regional Government of Junin that technical conformity was granted to the completion of the work Construction of complementary environment in the Chilca Health Center, despite presenting constructive deficiencies, items partially executed and non-existent works amounting to S/ 80,118. This fact would not only compromise the quality of the health infrastructure, but also prevents the application of penalties for late payment to the contractor that could exceed S/ 230 thousand.
During the inspection detailed in Control Visit Report No. 025-2026-OCI/5341-SVC (assessment period April 22-28, 2026), the presence of moisture was detected in various parts of the roofs. Likewise, the multiple sinks in critical areas (emergency, delivery room, puerperium and topical) do not have the proper sealing or the necessary fixation to walls and pedestals.
The intervention confirmed that the electrical installations are not operational, failing to comply with the standards of the technical file. In turn, having signed the work compliance improperly, the entity runs the risk of not being able to demand payment of penalties in the amount of S/ 230,577, affecting public assets.
The report also indicates that the construction supervisor and the Regional Infrastructure Management failed to meet the deadlines to form the reception committee. This administrative negligence delays the official delivery of the work and, therefore, postpones the medical attention that the population of Chilca urgently requires.
The project was executed with a total investment of S/ 2,562,084. Although the execution period expired on March 7, 2026, the current conditions of the infrastructure do not reflect the satisfactory completion of the contract.
The Comptrollers Office has communicated these results to the head of the Regional Government of Junin so that immediate corrective actions can be initiated and the corresponding responsibilities for having accepted a work with visible deficiencies be defined.
Junin, May 19, 2026
Communications Management
PRESS RELEASE Ndeg 503-2026-CG/GCOM