Actions were carried out by the personnel of the Electric Power DivisionPersonnel of the Electric Power Division carried out the maintenance of turbine No. 2 of the Viru hydroelectric power plant to guarantee the electricity generation and service provided by the installation, said the Manager of the Special Project Chavimochic (PECH).
We have proceeded with the corrective maintenance of turbine No. 2 of the C.H. Viru. This activity is important to guarantee its efficiency and prolong its useful life, said the PECH manager. Among the work developed, after the inspection, blades, rotor and other components were carried out to eliminate everything that may affect its performance. Subsequently, the status of the bearings, adjusting bolts and screws, also an analysis of the vibrations in order to detect failures that could affect the turbine.
During the disassembly of the turbine, it was possible to appreciate that the guidelines were totally uncalibrated, outside their normal position. Thus, it proceeded to repair and replace damaged or worn components, in order to maintain the efficiency and safety of the turbine. As is known, C. H. Viru has three pelton turbines, and each of them generates up to 3.5 kW
Electrical breakdowns are remedied
On the other hand, it was reported that the DEE personnel were working on the maintenance of electrical breakdowns in the networks of the transmission line that supplies electricity to the Tanguche area.
Among the maintenance work, to the networks of the isolated system, were the cleaning of the networks, insulators, and the respective change in the case that were damaged.