📋 Tender Overview
GORESAM will pave 2.6 kilometers in the upper part of Tarapoto, benefiting more than 10 thousand residents and improving access to tourist areas and the PEHCBM.The Regional Government of San Martin will carry out a 2.6-kilometer paving project in the upper part of Tarapoto, with an investment of close to 18 million soles, benefiting approximately 10,000 residents and improving urban connectivity to strategic sectors and tourist attractions such as the Taytamaki viewpoint and the Ahuashillo waterfall.
The intervention will be executed through the Huallaga Central and Bajo Mayo Special Project (PEHCBM) and includes the road improvement of the Putumayo, Proyecto and Vista Hermosa streets, important access roads for the residents of the Tarapotillo neighborhood and surrounding areas.
According to the project, the asphalting in the Putumayo jiron will cover from block 1, at the intersection with Circunvalacion Avenue, to block 8. Likewise, the Proyecto jiron will be intervened until block 9, where it will connect with the Vista Hermosa jiron. On this last road, three additional blocks will also be improved, allowing a direct connection with the San Pedro street and optimizing vehicular and pedestrian traffic throughout the area.
The general manager of the PEHCBM, engineer Javier Sinti Flores, reported that this work will be possible thanks to the agreement signed between the Regional Government of San Martin and the Provincial Municipality of San Martin, through which the PEHCBM will assume the preparation of the technical file, the financing and the execution of the project.
In addition to the impact on urban mobility and transportation, the work will strengthen tourism development in the upper part of Tarapoto, facilitating access to natural destinations that receive a permanent influx of visitors.
As scheduled, the technical file will be completed during the first week of June and the call process will last approximately 45 days, with the aim of starting work next August.