📋 Tender Overview
Regional governor congratulated the PET technical team that prepared the prefeasibility study.The Cardos Reservoir already has a birth certificate, after yesterday, Thursday, November 20, the project profile was approved on the Invierte.pe portal with the Unique Investment Code (CUI) 2700302, for the international tender promoted by the Central Government through the government-to-government modality.
This achievement was greeted this Friday by the regional governor, Luis Torres Robledo, who, together with advisors, the PET Board of Directors and officials, congratulated the work team that prepared the pre-investment study of the Cardos Reservoir.
My thanks to the community of Chipispaya, which has helped us a lot on this issue; to the Board of Irrigators of Sama, which has also supported, and to all those who have allowed us to have this profile. After this, the profile will be sent to the Ministry of Agriculture and the Ministry of Economy and Finance so that it can be included in the international tender and we will look for the country that will carry out the project, he highlighted.
In Government settings, the authority received the technical staff led by Eng. Vianey Torres Alferez and made up of professionals Denis Llanos Cahue, Hismael Rodriguez Illachura, Claver Huancollo Vilca, Orlando Gonzales Apaza, Zenon Pacoricona Sanga, Luis Roque Caballero, Diana Ortega Arias, Roberth Acero Choque, Carlos Paxi Mamani, Renato Portugal Tacora and Lucero Matamoros Luque; as well as the members of the PET Formulation and Evaluation Unit headed by Aldo Gambetta Montalvo, who delivered the documents of the studies carried out between 2024 and 2025.
The project is called Hydraulic infrastructure in the districts of Tacna and Inclan, in the province of Tacna, in the department of Tacna. It is a multipurpose investment that guarantees the availability of water for irrigation in the Sama Valley and the continuity of the drinking water service for the urban population of the city of Tacna.
By 2050, the work plans to benefit 434,314 residents who do not have continuity of drinking water service and 6,041 people who are dedicated to agricultural activity in the Sama Valley, with a total of 430,355 beneficiaries. According to the profile, the total viable investment cost would be S/ 1,766,895,401.2.
The project contemplates component 01: provision of infrastructure for the storage of water resources, which includes the construction of a catchment structure (intake) in the Coropuro sector, for a flow of 5 m3/s; construction of two sand traps; conduction line with a flow rate of 5 m3/s and a length of 62,296 km.
It also includes the construction of the Embalse Cardos storage infrastructure with a capacity of 30 cubic hectometers; construction of a distribution network for a flow rate of 0.7 m3/s and a length of 19,122 km, and a drinking water pipeline with a length of 34,418 km.
Meanwhile, component 02, referring to the adequate management of hydraulic infrastructure, considers the implementation of human capacity (training) of the provisioning system for the purposes of human population and water resources for agricultural irrigation.
This project will be located in the Puquio sector, in the Sama basin, 22 kilometers from the Pan-American Highway, at an altitude of 1,200 m above sea level. n. m., in the district of Inclan.
It was born in the current administration of the regional governor of Tacna, to solve the water shortage in the region. The studies began in June 2024 with a payment to the land at the site and was included as a flagship project by the Central Government through Ministerial Resolution No. 0137-2025-MIDAGRI, on April 25 of this year.
In July, the Cardos Reservoir has been included in the package of hydraulic projects of the Ministry of Agrarian Development and Irrigation (Midagri) and, at the beginning of November, delegations from Korea, Japan, Canada, Spain and the United Kingdom visited Tacna to see in situ the place where it is planned.