📋 Tender Overview
The District Municipality of Paucarpata today completed the placement of the new asphalt layer on Maria Nieves y Bustamante Avenue, as part of the road resurfacing work. The intervention includes 5,448.24 square meters of improved surface, with a 2-inch thick layer that optimizes the conditions of the road.
This progress is integrated into the surface milling previously carried out and is part of the maintenance sheet that has a budget of S/ 643,827.96 and an execution period of 30 calendar days. The works include the construction of humps, horizontal signage, cleaning and removal of excess material to guarantee a safer and orderly road.
With these actions, the commune continues to improve walkability in this and other areas of the district, offering safer, more fluid and suitable routes for all residents.